I-15 Express Lanes: Construction Update, Week of July 8-12

Post Date:07/09/2019 8:00 AM

SOUTHBOUND I-15 NIGHTTIME CLOSURE SCHEDULED WEDNESDAY, JULY 10

FULL CLOSURE: Southbound I-15 between Hidden Valley Pkwy. and State Route 91 will be closed Wednesday, July 10 at 11 p.m. to Thursday, July 11 at 5 a.m. to allow crews to safely remove an overhead sign.  Motorists will be detoured to exit Hidden Valley Pkwy. and proceed onto Main St. Detour signs will be clearly marked.   

NIGHTTIME RAMP, CONNECTOR CLOSURES

Intermittent lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60, from 8 p.m. to 5 a.m., weeknights. During lane reductions, at least one lane will remain open at all times.   
The 15/91 Express Lanes Connector and #1 General Purpose Lane are scheduled to be closed nightly, 8 p.m. to 5 a.m, through Thursday, July 11. 
 
The following closures are also scheduled: 

Monday, July 8, 9 p.m. to 5 a.m. 
Eastbound 91 to Northbound 15 Connector
Northbound 15 Hidden Valley On-ramp

Tuesday, July 9, 9 p.m. to 5 a.m. 
Eastbound 91 to Northbound 15 Connector

 

Wednesday, July 10, 9 p.m. to 5 a.m.
Southbound 15 Hidden Valley On-ramp

Thursday, July 11, 9 p.m. to 5 a.m.
Eastbound & Westbound 91 to Southbound 15 Connector

Friday, July 12, 10 p.m. to 6 a.m. 
Eastbound 91 to Northbound 15 Connector
Northbound 15 Magnolia Ave. On-ramp

STREET LANE REDUCTIONS

Sixth Street:  There will be nightly lane reductions from 8 p.m. to 5 a.m. through Thursday, July 11.
Second Street: Intermittent daytime flagging is planned from 6 a.m. to 2 p.m. through Thursday, July 11 for striping work.

 

About the 15 Express Lanes Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. For more information visit the project webpage at www.15project.info.

Due to the dynamic nature of construction, this information is subject to change.  If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.


Neighboring Projects

91 Express Lanes Weekend Closures: Tentative closures on the westbound 91 Express Lanes and #1 General Purpose Lane are scheduled Friday night, July 12.
Cajalco Rd. / I-15 Interchange Improvement Project: Alternating freeway lane and ramp closures are scheduled. Visit i15cajalco.com for closure information. 
Limonite Ave / I-15 Interchange Improvement Project: The Park and Ride Lot by Limonite Ave. will remain closed through October. Visit i15limonite.org for closure information. 

 


Date, Time
Location
Monday, June 24
9 p.m. to 5 a.m. 
Westbound 91 to Southbound 15 Connector

Southbound 15 
Magnolia Ave. Off-Ramp
Tuesday, June 25
9 p.m. to 5 a.m. 
Eastbound 91 to Northbound 15 Connector