I-15 Express Lanes: Construction Update- Week of April 15, 2019

Post Date:04/13/2019 11:00 AM

There will be no lane or ramp closures Friday, April 19 through Sunday, April 21 in observance of the Easter weekend.

NIGHTLY CONNECTOR CLOSURES

15/91 Connector closures are scheduled from Monday, April 15 to Thursday, April 18 from 8 p.m. to 4 a.m. nightly. Detours will be clearly marked; visit our detour map for more information. The scheduled closures are as follows: 

Monday, April 15: 15 Southbound to 91 Westbound
Tuesday, April 16 - Thursday, April 18: 91 Eastbound to 15 Southbound

NIGHTTIME LANE & RAMP CLOSURES

Intermittent lane reductions are scheduled on northbound and southbound I-15, between Weirick Rd. and SR-60, from 8 p.m. to 5 a.m. weeknights. During lane reductions, at least one lane will remain open at all times. Ramp closures are scheduled from 9 p.m. to 5 a.m. nightly: 

Monday, April 15: SB 15 Hidden Valley Pkwy. on-ramp
Tuesday, April 16 - Wednesday, April 17: SB 15 Second St. on-Ramp
Thursday, April 18: SB 15 Sixth St. on- and off-ramp and SB 15 Ontario Ave. on-ramp

 

NIGHTTIME FLAGGING ON EAST SIXTH STREET

Crews will be flagging on E. Sixth St. in Corona from Monday, April 15 to Friday, April 19 from 8 p.m. to 5 a.m. nightly for demolition work. Please allow extra time and use caution when traveling through the area.

TEMPORARY TRAFFIC CONFIGURATION ON EL CERRITO ROAD

A temporary traffic configuration is in place through summer on El Cerrito Road at I-15 to allow crews to widen the bridge. Please allow for extra travel time and use caution when traveling through the area. 

Construction Update - Week of March 4, 2019

NEIGHBORING PROJECTS

Cajalco Rd. / I-15 Interchange Improvement Project:
Lane reductions are expected at Cajalco Ave. over the next several weeks. Visit i15cajalco.com for more information. 

Limonite Ave / I-15 Interchange Improvement Project: 
Full freeway closures are expected on the 15 at Limonite Ave. over the next few weeks. Visit i15limonite.org for dates and more information.   

 

About the 15 Express Lanes Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. Due to the dynamic nature of construction, this information is subject to change.

For more information, visit the project website, call the project helpline at (844) 415-9777, or send an email to 15project@rctc.org.


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 