Inner Circle News header

Icon - City News 1
Icon - Press Releases 1   Icon - Public Safety 1   Icon - Community 2    Icon - Events 2  

 

Print
Press Enter to show all options, press Tab go to next option

Construction Alert: Cajalco Road / I-15 Interchange Improvement Project Southbound I-15 Full Closure

Post Date:03/07/2019 10:30 AM

CONSTRUCTION ACTIVITIES:

Crews will work over several nights (weeks) to safely remove the steel beams (falsework) used to form the new Cajalco Rd Bridge.

What to expect:*

• Over the next four weeks, the contractor will fully close the I-15 freeway in one direction at a time. Weekly updates will be provided.
• Please be advised, work may be noisy due to construction equipment moving on- and off-site, equipment back up alarms, and other construction-related noise.
• Temporary lighting will be used to illuminate areas around the work zone.
• All closures are weather permitting. If inclement weather occurs, the closures will be automatically cancelled and rescheduled.
• Access will be provided for emergency services during the closures.

NIGHTTIME ROADWAY, FREEWAY LANE RESTRICTIONS AND RAMP CLOSURES*

Monday - Thursday, March 11 - March 14 • 8 PM - 4 AM

Full Freeway Closure (10 p.m.) 
Southbound I-15 from El Cerrito Rd to Weirick Rd/Dos Lagos Dr

Local Roadway Restrictions
Cajalco Rd. and the Cajalco Rd Bridge will be CLOSED between Grand Oaks/Cajalco Rd and Bedford Canyon Rd/Cajalco Rd Intersection

Full Ramp Closures
Southbound I-15 On-and off-ramps at Cajalco Rd
Southbound I-15 On-Ramp at El Cerrito Rd                
Northbound I-15 On-ramp at Cajalco Rd

Alternating Lanes
Northbound I-15 from Weirick Rd/Dos Lagos Dr to El Cerrito Rd

- Detour signs will be posted. Detour map is below.
- Northbound I-15 will have one lane OPEN
- Northbound I-15 Off-Ramp at Cajalco Rd will remain OPEN

*Note: Due to inclement weather or unforeseen issues, these dates and times are subject to change without notice. If inclement weather occurs, freeway closures be automatically canceled and rescheduled. All closures are as-needed and weather permitting.

Construction Alert | March 11 - 14, 2019 | Southbound I-15 Full Closure

 

About this Project

The Cajalco Road/ I-15 Interchange Improvement Project will widen Cajalco Road from two to six lanes from Temescal Canyon Road to Bedford Canyon Road. The project also proposes several improvements to the entrance and exit ramps and auxiliary lanes. Visit the Project website http://i15Cajalco.com for the latest information.

 

Return to full list >>

 


Your source for official City News