I-15 Express Lanes: Construction Update - Week of Feb. 4, 2019

Post Date:02/04/2019 8:15 AM

CONSTRUCTION RECAP: JANUARY 2019

Check out the latest construction progress on the 15 Express Lanes! 

Construction Update - Week of Feb. 4, 2019

NIGHTTIME 15/91 CONNECTOR CLOSURES

Crews will be closing the 15/91 connectors nightly from Monday, Feb. 4 to Friday, Feb. 8 for crane assembly and dirt haul work. 

 Date, Time CONNECTOR
 
Monday, Feb. 4 - Thursday, Feb. 7 from 9 p.m to 5 a.m.
  • 91 Westbound to 15 Southbound 
  • 91 Eastbound to 15 Southbound 
Friday, Feb. 8 from 10 p.m. to 7 a.m.
  • 91 Westbound to 15 Southbound 
  • 91 Eastbound to 15 Southbound 

Detours will be clearly marked. Visit our detour map for more information. 

NIGHTTIME RAMP CLOSURES

The following ramp closures are scheduled on the 15 Express Lanes project: 
DATE, TIME  LOCATION  DETOUR
Monday, Feb. 4
9 p.m to 5 a.m.

Southbound I-15 Hidden Valley on-ramp 

Use Second St.
Wednesday, Feb. 6 - Thursday, Feb. 7
9 p.m. to 5 a.m.

Southbound I-15 Hidden Valley on-ramp

Use Second St. 
 
Friday, Feb. 8
9 p.m. to 6 a.m. 
Southbound I-15 Hidden Valley on-ramp Use Second St. 

Detours will be clearly marked. Visit our detour map for more information. 

Construction Update - Week of Jan. 21, 2019

DAYTIME FLAGGING ON CORONA AVE.

Daytime flagging operations will be in place on Corona Ave. at I-15, near Parkridge Ave., for bridge widening work. Flaggers will be directing motorists through the area. Work is expected to last through March. 

Construction Update - Week of Jan. 21, 2019

 

NIGHTTIME LANE REDUCTIONS

Intermittent lane reductions may occur on northbound and southbound I-15 from 8 p.m. to 5 a.m. weeknights and up to 7 a.m. weekend mornings. At least one lane will remain open at all times.    

 

About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. Due to the dynamic nature of construction, this information is subject to change.

For more information, visit the project website, call the project helpline at (844) 415-9777, or send an email to 15project@rctc.org.


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 


About the Project

The 15 Express Lanes project will add two tolled express lanes in each direction on I-15 between Cajalco Road and SR-60, a distance of approximately 15 miles. Drivers will be able to enter and exit the tolled facility at multiple locations, and the project continues RCTC's ongoing commitment to expand the express lanes network. Construction in the median began in March 2018. The new lanes are expected to open in 2020. 