PROJECT UPDATE: Paving Work on Lincoln Avenue, Main Street, and River Road

Post Date:11/01/2018 2:15 PM

Paving Work on Lincoln Avenue, Main Street & River Road Project Update

As part of the 2017* Street Pavement Maintenance & Rehabilitation Project, Lincoln Avenue from Parkridge Avenue to Rincon Street, Main Street from Grand Boulevard to Hidden Valley Parkway, and River Road from Corydon Street to Main Street are being paved. Please be advised that traffic delays are to be expected. This project  is funded through SB1.

Project Update as of Thursday, November 1:

The majority of work on Main Street has been completed.

Lincoln Avenue paving has been completed and is expected to be striped by the end of the week.  

River Road grinding and paving will continue into next week. Drivers should give extra time as lane reductions will continue possibly into Saturday, November 10 as crews complete this phase of the work. Striping of River Road will be completed about a week after the pavement has been completed. 

Location:

Lincoln Avenue from Parkridge Avenue to Rincon Street, Main Street from Grand Boulevard to Hidden Valley Parkway, and River Road from Corydon Street to Main Street

Duration:

September 17, 2018 – November 19, 2018

Work Hours:

  • Phase I: Working hours to remove first median at Main Street south of River Road are from 8:00 AM to 5:00 PM.
  • Phase II: Working hours along Main Street northbound direction and southbound direction from Grand Boulevard to Hidden Valley Parkway are from 8:00 p.m. to 5:00 a.m..
  • Phase III: Working hours along River Road north-west bound direction and south-east bound direction from Main Street to Corydon Street are from 8:00 a.m. to 4:30 p.m.
  • Phase IV: Working hours along Lincoln Avenue northbound direction and southbound direction from Parkridge Avenue to Rincon Street are from 8:00 a.m. to 4:30 p.m.

Traffic Impacts & Advisories During Construction:

  • Lane reductions with at least one lane open on Lincoln Avenue from Parkridge Avenue to Rincon Street, Main Street from Grand Boulevard to Hidden Valley Parkway, and River Road from Corydon Street to Main Street.
  • Noise levels will be monitored to ensure work performed is within the necessary compliance levels.
  • Please obey all posted construction signs, speed limits, drive safely and do not enter the construction work zone.
  • Please plan accordingly by taking alternate routes and allowing more travel time for known delays in traffic.

For additional information, contact Project Manager, Barry Ghaemi at (951) 739-4961 or Barry.Ghaemi@CoronaCA.gov.

We appreciate your patience and cooperation through this inconvenience.

 Note: Construction schedules are subject to change for various reasons including but not limited to: weather conditions, unforeseen emergencies and other acts of nature.

*This project was initially scheduled for the 2017-2018 fiscal year. 